Iaat Wastewater Treatment Plant

Wastewater treatment + reuse, 12,000 m3/day design capacity; up to 8,000 m3/day treated at project closing in 2012 in Lebanon.

Stalled

The record

Country
Lebanon
Location
Iaat
Coordinates
34.049, 36.145
Technology
Wastewater treatment + reuse
Capacity
12,000 m3/day design capacity; up to 8,000 m3/day treated at project closing in 2012
Capital cost
US$49 million
Stage
Stalled
Owner or client
Council for Development and Reconstruction
Contractor
—
Operator
Bekaa Water Establishment
Finance
World Bank
Award or start year
2002
Commissioned
2011

Record last checked 2026-09-18.

History

Sources

7 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. World Bank, Lebanon Ba'albeck Water and Wastewater Project, Implementation Completion and Results Report (12 Dec 2012). documents.worldbank.org.
  2. The Iaat plant did not start operations until the sewerage network was complete in late 2009, then stopped because it received only 300 to 700 m3/d against an operational minimum of 2,000 m3/d for a plant designed for 12,000 m3/d; all connections were complete by 2010 but an average of only 1,500 m3/d reached the plant; regular operations commenced in 2011 after reconciliation with farmers who had irrigated with untreated wastewater; at project closing the plant was receiving and treating up to 8,000 m3/day.
  3. The plant itself was built under the earlier Emergency Reconstruction and Rehabilitation Project, so the budget figure covers the network and operations project.
  4. World Bank, project detail P074042. projects.worldbank.org.
  5. Board approval 4 June 2002, closing 15 June 2012, project cost US$49.63 million.
  6. Karim Eid-Sabbagh, Water Alternatives 16(2) (2023). water-alternatives.org.
  7. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

Records the plant as World Bank funded for the Baalbek area, designed with reuse in mind but with no reuse network funded, and carries the Bekaa Water Establishment's 2020 statement. Coordinates from OpenStreetMap. Condition after 2020 was not established, and Baalbek was heavily struck during the 2024 conflict.