Bisri Dam

Dam and water supply scheme, 125 million m3 reservoir (design); dam never built in Lebanon.

Stalled

The record

Country
Lebanon
Location
Bisri
Coordinates
33.575, 35.508
Technology
Dam and water supply scheme
Capacity
125 million m3 reservoir (design); dam never built
Capital cost
US$617 million
Stage
Stalled
Owner or client
Council for Development and Reconstruction
Contractor
None mobilised; the World Bank recorded that the contractor had not been mobilised at the worksite
Operator
—
Finance
IBRD loan US$474m; Islamic Development Bank US$128m; Government of Lebanon US$15m
Award or start year
2014
Commissioned
—

Record last checked 2026-09-18.

History

Sources

7 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. World Bank, Lebanon Water Supply Augmentation Project (Bisri Dam) programme page. worldbank.org.
  2. Storage 125 million cubic meters; total cost US$617 million; site 35 kilometers south of Beirut immediately upstream of the village of Bisri; 26 km gravity tunnel with treatment at Wardanieh; over 1.6 million beneficiaries.
  3. World Bank, Cancellation of Water Supply Augmentation Project statement (4 Sep 2020). worldbank.org.
  4. The government submitted a draft Ecological Compensation Plan on 12 August 2020 and the Bank's 25 August comments were not addressed to its satisfaction; the contractor had not been mobilized at the worksite.
  5. World Bank, Bisri Dam project cancellation factsheet (Sep 2020). worldbank.org.
  6. US$244 million cancelled effective 5 September 2020; about US$197 million disbursed; 861 landowners paid US$155 million in expropriation fees; partial suspension from 26 June 2020. World Bank, project detail P125184. projects.worldbank.org.
  7. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

Board approval 30 September 2014; implementing agency the Council for Development and Reconstruction; closed 30 June 2024. Coordinates from the OpenStreetMap way for the Bisri dam site. The dam height of 73 m circulating in secondary summaries could not be confirmed and is omitted.