Taweelah A1 IWPP

MSF/MED + power, 84.8 MIGD (about 386,000 m3/day); MED 53 MIGD and MSF 32 MIGD in United Arab Emirates.

Operational

The record

Country
United Arab Emirates
Location
Al Taweelah, Abu Dhabi
Coordinates
24.761, 54.680
Technology
MSF/MED + power
Capacity
84.8 MIGD (about 386,000 m3/day); MED 53 MIGD and MSF 32 MIGD
Capital cost
US$1.5 billion
Stage
Operational
Owner or client
Gulf Total Tractebel Power Company (TAQA 60%, TotalEnergies 20%, Engie 20%); offtaker EWEC
Contractor
—
Operator
Total Tractebel Emirates O&M
Finance
Independent water and power project, about US$1.5 billion
Award or start year
2000
Commissioned
2003

Record last checked 2026-09-18.

History

Sources

5 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. Gulf News, Taweelah A1 commissioned. gulfnews.com.
  2. Abu Dhabi's second IWPP, US$1.5 billion, awarded in 2000 by ADWEA to a Total and Tractebel consortium holding 40% against ADWEA's 60%; the page carries an automated later timestamp, the report itself dates from the 2003 commissioning.
  3. Engie Middle East, Al Taweelah A1-10 asset fact sheet (2024). engiemiddleeast.com.
  4. 1,590 MW and 84 MIGD, technology CCGT and MED, PCOD 2003 with a 2009 extension, offtaker EWEC, PWPA to July 2029. TRANSCO, 2019 Seven Year Water Planning Statement (2020-2026), June 2019, Table 4.3 Existing Production Plant Site and Capacities by Technology. saudigulfprojects.com.
  5. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.