Sheikh Saied Wastewater Treatment Plant

Wastewater treatment, About 350,000 m3/day, serving around 2 million people in Aleppo in Syria.

Planned

The record

Country
Syria
Location
Aleppo
Coordinates
36.139, 37.144
Technology
Wastewater treatment
Capacity
About 350,000 m3/day, serving around 2 million people in Aleppo
Capital cost
—
Stage
Planned
Owner or client
Syrian Arab Republic represented by the Ministry of Finance
Contractor
—
Operator
—
Finance
IDA grant within the US$150 million World Bank Syria Emergency Water Security and Resilient Services Project
Award or start year
2026
Commissioned
—

Record last checked 2026-09-18.

History

Sources

2 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. World Bank, Syria Emergency Water Security and Resilient Services Project (P515199), Project Information Document, Appraisal Stage (19 Mar 2026). documents1.worldbank.org.
  2. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

The component covers preparing for the rehabilitation of the Sheikh Saied WWTP in Aleppo by advancing necessary assessments and procurement preparation for the eventual rehabilitation of the plant to its capacity of about 350,000 m3 per day, servicing another 2 million people in Aleppo; implementing agency the Ministry of Energy, Water Resources Directorate. Only assessments and procurement preparation are financed at this stage, so no works value exists. Coordinates from the OpenStreetMap wastewater plant polygon tagged in Arabic as the Sheikh Saied treatment station. Current condition was not established.