Jubail 5 SWRO (Jubail 2 Replacement)

Seawater RO, 1,000,000 m3/day in Saudi Arabia.

Operational

The record

Country
Saudi Arabia
Location
Jubail
Coordinates
26.897, 49.773
Technology
Seawater RO
Capacity
1,000,000 m3/day
Capital cost
—
Stage
Operational
Owner or client
Saline Water Conversion Corporation, now the Saudi Water Authority
Contractor
Saudi Services for Electro Mechanic Works (SSEM) with Metito Saudi
Operator
Saline Water Conversion Corporation, now the Saudi Water Authority
Finance
—
Award or start year
2021
Commissioned
2025

Record last checked 2026-09-20.

History

Sources

6 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. SHARAKAT (Saudi Water Partnership Company), 7 Year Statement 2025-2031, March 2026, Riyadh, Eastern Province and Qassim table of current and under-development sources. sharakat.com.sa.
  2. lists "Jubail 5 (Jubail 2 RO-REPLACMENT)" as on production with a commercial operation date of 2025, a date out of 2060, a design capacity of 1,000,000 m3/day, a production factor of 0.98 and an export capacity of 980,000 m3/day; the source is given as MEWA. Saline Water Conversion Corporation, Annual Report 2022 (English), p. 79. swcc.gov.sa.
  3. lists among the projects it was then about to launch "Replacing Al-Jubail plant (2) with a design capacity of up to one million cubic meters per day". Saudipedia (Saudi Ministry of Media national encyclopaedia), Production of Desalinated Water in Saudi Arabia. saudipedia.com.
  4. states that SWCC signed a contract in 2021 with Saudi Services for Electro Mechanic Works (SSEM) and Metito Saudi Ltd to replace the outdated technologies and assets of the al-Jubayl phase 2 system with reverse osmosis, producing one million m3 a day for Riyadh province and set to start production in 2024. Published start dates therefore differ, 2024 in Saudipedia and 2025 in SHARAKAT's table; the SHARAKAT commercial operation date is used because it is the later and more specific statement.
  5. This is a different scheme from the register's existing Jubail Phase 2 SWRO (Jubail RO2) row, which is the 400,000 m3/day plant built by SEPCO III with Metito and commissioned in 2022. Coordinates from OpenStreetMap way 555199312, Jubail Power and Desalination Plant. openstreetmap.org.