Basra Water Supply Improvement Project

Water treatment plant, 608,000 m3/day target supply for Basra and Hartha against a 2007 baseline of 412,200 m3/day; the Hartha phases 3 and 4 are rated 199,000 m3/day; first-phase transmission main 37 km in Iraq.

Under construction

The record

Country
Iraq
Location
Basra
Coordinates
—
Technology
Water treatment plant
Capacity
608,000 m3/day target supply for Basra and Hartha against a 2007 baseline of 412,200 m3/day; the Hartha phases 3 and 4 are rated 199,000 m3/day; first-phase transmission main 37 km
Capital cost
—
Stage
Under construction
Owner or client
Ministry of Construction, Housing, Municipalities and Public Works, General Directorate of Water
Contractor
—
Operator
Basra Water Directorate
Finance
JICA yen loan of 42,969 million yen against a total project cost of 72,944 million yen
Award or start year
2008
Commissioned
—

Record last checked 2026-09-18.

History

Sources

5 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. JICA, Ex-ante Evaluation, Basrah Water Supply Improvement Project. www2.jica.go.jp.
  2. Loan agreement 11 June 2008 for 42,969 million yen against a total project cost of 72,944 million yen; borrower the Government of Iraq and executing agency the Ministry of Municipalities and Public Works; scope is rehabilitation and construction of water treatment plants, improvement of distribution networks and consulting services; schedule July 2008 to November 2014; the twelve existing Basrah plants had a combined 412,000 m3/day against peak demand of about 914,000 m3/day, and the target was 608,000 m3/day by 2016 with supply hours rising from 12 to 24 and leakage falling from 50 to 30 per cent.
  3. Zawya Projects, Iraq completes Phases 3 and 4 of Great Basra Water Project. zawya.com.
  4. Full design capacity 199,000 m3/day; client the Ministry of Construction, Housing, Municipalities and Public Works; covers Basra and Haritha. 964media, Basra's main water pipeline passes two-thirds completion. en.964media.com.
  5. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

First-phase transmission main of 37 km at 86.5 per cent with 26.5 km laid as of 11 July 2026; client the General Directorate of Water.