Beni Haroun Dam and Transfer

Dam and interbasin transfer, 0.963 km3 reservoir; transfer pumping station rated 23 m3/s with two 100 MW pumps, which are pumping plant and not generation in Algeria.

Operational

The record

Country
Algeria
Location
Mila
Coordinates
36.567, 6.275
Technology
Dam and interbasin transfer
Capacity
0.963 km3 reservoir; transfer pumping station rated 23 m3/s with two 100 MW pumps, which are pumping plant and not generation
Capital cost
US$98 million
Stage
Operational
Owner or client
Agence Nationale des Barrages et Transferts; Ministère des Ressources en Eau
Contractor
Dragados for the dam and the intake tower; Alstom and Dragados y Construcciones for the pumping station; Societa Italiana per Condotte d'Acqua for the pressure main to Oued Athmenia
Operator
Agence Nationale des Barrages et Transferts
Finance
Arab Fund for Economic and Social Development for the pumping station
Award or start year
2002
Commissioned
—

Record last checked 2026-09-18.

History

Sources

6 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. Dragados, Beni-Haroun Dam. dragados.com.
  2. The contractor's own sheet gives a straight gravity dam in roller-compacted concrete on the El-Kebir river, 118 m high, 714 m crest, 1.6 million m3 of roller-compacted concrete and 1.9 million m3 of concrete in all, 963 hm3 of reservoir, for water supply, irrigation and flood control, and the largest roller-compacted concrete dam in the world when built.
  3. MEED, Beni Haroun project takes shape. meed.com.
  4. The pumping station is rated 23 m3/s with two 100 MW pumps and two 100 MVA motors from Alstom and an 80 m intake tower 30 m across from Dragados; the engineer procure construct contract to the Alstom and Dragados y Construcciones consortium was 110 million euros, about 98 million dollars, with a separate ten-year operation and maintenance contract to Alstom at 32 million euros, about 28.5 million dollars, financed by the Arab Fund for Economic and Social Development; site work began in January 2002 and operation was expected at the end of 2004. MEED normally bot-walls readers, but this page returned 200 and full text.
  5. IN.CO. Ingegneri Consulenti, Beni Haroun. inco-eng.com.
  6. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

Detailed executive design of the pressure main from the pumping station to Oued Athmenia, 2004 to 2006, for Societa Italiana per Condotte d'Acqua of Rome as contractor, under the Ministry of Public Works. Coordinates of the dam wall from OpenStreetMap way 109563032, tagged waterway=dam.