Case study
The regulator that owns the plants: Saudi Arabia’s water restructuring
Saudi Arabia split policy, regulation, procurement and transmission into separate bodies between 2018 and 2026. The central act, moving the state desalination fleet out of the regulator’s hands, has still not been completed.
- Policy
- Ministry of Environment, Water and Agriculture1
- Procurement
- Saudi Water Partnership Company, trading as Sharakat4
- Transfer ordered by
- Council of Ministers Resolution 652, 21 June 20221
- Time elapsed without transfer
- More than four years1
- Staff still in the regulator’s production arm
- about 5,0001
Context
Until recently one body did almost everything. The Saline Water Conversion Corporation was the world’s biggest producer of desalinated water, and it also held the transmission and storage assets.51 Regulation sat split between the ministry and the Water and Electricity Regulatory Authority.6 Vision 2030 called for that to be pulled apart, with private capital taking production.64
The pulling apart happened on paper. Council of Ministers Resolution 652, of 21 June 2022, ordered the transfer of the corporation’s production, transmission and storage assets to a Public Investment Fund vehicle, the Water Solutions Company.17 In May 2024 the corporation itself was renamed the Saudi Water Authority and given the sector regulator’s mandate.23 Water functions were removed from the electricity regulator, which became the Saudi Electricity Regulatory Authority.6
The design
The intended shape is conventional and sound. The ministry sets policy.1 The Saudi Water Authority licenses, sets standards and approves tariffs under the 2020 Water Law.268 Sharakat procures independent water and sewage plants against long-term offtakes.4 A state transmission company is due to take over pipeline procurement, and the National Water Company runs urban services.1 Production moves to a separate company that sells under purchase agreements.1
Sharakat publishes a seven-year statement with quarter-level milestones for 53 projects.4 That makes it unusually transparent for a procurer in the region, and auditable against its own plan. Its stated target is complete private participation in desalinated water production by 2030.4
What worked
Competitive procurement compressed tariffs hard. Across the Gulf they fell from above US$1.00 a cubic metre under thermal distillation to below US$0.40 under independent water projects. That would not have happened under a state monopoly.9 The pressure persists: Vision Invest’s preferred bid for the Riyadh to Qassim pipeline in December 2025 came in almost 20 per cent below the next nearest.10
Regulation is now one counterparty rather than several, which the law firm Al Tamimi identifies as the practical gain for investors.6 The pipeline delivered assets too. Nine Sharakat desalination plants were in operation by the 2025 statement.4 Inside the state fleet, the authority says it raised the capacity of more than 400 inland plants by over 1.5 million cubic metres a day in two years.11
What did not, or is unresolved
The regulator still owns and operates the assets it regulates. This is documented rather than inferred. Pinsent Masons wrote in October 2025 that the authority’s production arm still runs most of the former SWCC facilities, with around 5,000 staff.1 It warned investors to understand bodies performing overlapping regulatory and operational functions.1 Saudipedia’s entry on the authority says the same thing from the other side: the authority operates the production assets until they are transferred.12
The transfer was ordered more than four years ago.1 The corporation’s governor said in June 2022 it would take 18 to 20 months, possibly three years.13 In August 2026 the production arm handed management of more than 400 groundwater and surface water plants to Al Holol Water Desalination Company. Its own staff still run them day to day.11
One caveat, stated plainly because the alternative is manufacturing a critique. No source reviewed for this case calls this a conflict of interest. The legal commentary consulted offers only Pinsent Masons’ descriptive phrase, and the fact itself.16
Privatisation was abandoned rather than completed. The cabinet approved selling eleven plants in September 2019.95 Seven companies and consortia were invited to bid for a 60 per cent stake in Ras Al Khair.14 The facility cost more than US$7 billion to build, and the sale was expected to raise about US$2 billion.15 The sale was suspended in July 2021.1415
The published plan is also slipping against itself, which only transparency reveals. Between the 2024 and 2025 statements all seven planned desalination plants had their tender dates pushed back.164 Six saw their operation dates slip, fifteen project-years in all.164 Rabigh 5 now lands in 2033, beyond Vision 2030.4 Riyadh North, a sewage plant dated for 2029 in the 2024 edition, now has no dates at all.164 The procurer lengthened its own tendering assumption from 12 to 14 months out to 18 to 24.164 Saudi water infrastructure awards in the first half of 2026 were US$3.14 billion, against US$7.58 billion a year earlier.17
What it means for the next one
Legal ownership and strategic control are not the same thing, and the interesting cases pull them apart. At Hidd, Bahrain decides what gets built, to what specification and at what tariff, while a private developer owns the plant.189 Saudi Arabia owns its assets, regulates the market and sets its contractors’ targets, while still procuring new capacity privately.9 Either can work. Confusing the two is what does not.
Mhamed Biygautane of the University of Melbourne argues that Gulf governments are quietly reasserting sovereign control over the strategic core of the water system. Water is being reclassified from a tradeable utility service into a national security asset.9 He gives three determinants: fiscal headroom, because strong balance sheets reduce the appetite for off-balance-sheet structures. Strategic sensitivity, because desalination sits closer to defence than to electricity in the Gulf. And institutional learning, because procurement agencies can now unbundle risk themselves.9
The boundary condition is money. Re-sovereignisation is a choice available to governments that can afford it. For everyone else the concession model remains the way to keep a plant off the sovereign balance sheet.9 That is precisely why Bahrain tendered its first independent water project rather than building the plant itself, carrying government debt of 133 to 142 per cent of GDP.199
Sources
19 references
Bahrain’s debt range is as reported by Smart Water Magazine; the IMF releases could not be retrieved. The August 2026 Al Holol agreement covers management of inland plants, not transfer of ownership.
- Pinsent Masons, “The regulatory framework for Saudi Arabia’s water sector”, Out-Law guide, 31 October 2025. A practitioner guide, not the gazette.
- Saudi Water Authority, announcement of the Cabinet’s approval to transform the Saline Water Conversion Corporation into the Saudi Water Authority, 7 May 2024.
- Saudi Water Authority, “About us”, on Cabinet Resolution No. 918 of 28/10/1445H.
- Sharakat (Saudi Water Partnership Company), 7 Year Statement 2025–2031, March 2026.
- Smart Water Magazine, “Saudi Arabia stops privatization of SWCC”, 22 June 2022.
- Rafiq Jaffer and Aurangzeb Maqsood, Al Tamimi & Company, via Mondaq, “Saudi Water Sector Overhaul: Greater Regulatory Clarity And New Investment Opportunities”, 26 September 2025.
- Sarah Glubb and Nirmal Narayanan, Arab News, “Saudi Arabia stops privatization of world’s largest desalination firm; moves its assets to PIF-owned company”, 21 June 2022.
- Saudipedia, “Water in Saudi Arabia”, on the Water Law issued in 2020.
- Cristina Novo, Smart Water Magazine, “The sovereign desalination map: why governments are taking back ownership”, 29 May 2026, quoting Mhamed Biygautane.
- Smart Water Magazine (Sharakat release), “Vision Invest named preferred bidder for Riyadh–Qassim IWTP”, 26 December 2025.
- Cristina Novo, Smart Water Magazine, “Saudi Water Authority hands groundwater and surface water desalination plants to Al Holol Water”, 14 August 2026.
- Saudipedia, “Saudi Water Authority”.
- Sarah Glubb and Nirmal Narayanan, Arab News, “SWCC head expects water assets transfer to PIF-owned WSC to take up to 3 years”, 22 June 2022.
- Reuters via Yahoo Finance, “Saudi Arabia suspends privatisation of desalination and power plant”, 26 July 2021.
- Al Jazeera and Bloomberg, “Saudi Arabia suspends $2B sale of desalination plant”, 26 July 2021.
- Saudi Water Partnership Company, SWPC 7 Year Statement 2024–2030, Planning Division, 2024.
- Mark Dowdall, MEED, “Saudi water sector awaits next catalyst”, 2 July 2026, citing MEED Projects data.
- Electricity and Water Authority (Bahrain), “EWA Launches International Tender for 60 MIGD Hidd Independent Water Plant”, 31 July 2025.
- Jennifer Aguinaldo, MEED, “Al-Hidd IWP prequalification gets under way”, 3 January 2025.
Numbered references are linked from the superscript markers in the text. Figures without a marker come from the sources above as compiled in the site methodology.