Case study
Bahr El-Baqar: a record capacity, and the salt it cannot remove
Egypt built what was then the world’s largest drainage treatment plant in under two years, to irrigate Sinai. Its own national research institutes now report that the water arrives saltier than the law allows for reuse, and the plant removes no salt.
- Inaugurated
- 27 September 20211
- EPC contract
- US$739 million, signed May 20194
- State cost figure
- EGP 20 billion2
- Built by
- Arab Contractors and Orascom Construction, 50:505
Context
The Bahr El-Baqar drain has for decades been among the most polluted drainage systems in Egypt.1 It carries agricultural runoff, industrial effluent and municipal sewage north-east across the delta and empties into Lake Manzala. About 40 per cent of its flow is domestic and commercial wastewater.6 Sampling at the outlet in 2018 and 2019, by a team including the National Water Research Center’s environmental quality laboratory, found dissolved oxygen at 0.24 mg per litre and total coliforms of 43 x 10⁵ per 100 ml.6
Egypt wanted that water. The Sinai reclamation programme needed irrigation and the Nile allocation is fixed at 55.5 billion cubic metres a year.7 Treating a drain adds supply without taking Nile water from somebody else, so the drain became a resource and the plant became a flagship.8
The design
The Engineering Authority of the Armed Forces commissioned it.9 A fifty-fifty joint venture of the Arab Contractors and Orascom Construction built it under a US$739 million engineering contract signed in May 2019, with Acciona as process partner and Khatib and Alami leading design.5431 The Arab Fund approved a loan in May 2018 at 2.5 per cent, with six years of grace and thirty to maturity.10
The train is physico-chemical: rapid and slow mixing for coagulation and flocculation, settling, disc filtration, then ozone and chlorine.2 There is no biological stage and no membrane in the published process descriptions.32 Four treatment lines of 1.25 million cubic metres a day give the 5.0 million figure that Acciona and the lender both use.310 Four intake buildings rated at 1.4 million give the 5.6 million the state and Guinness use.112 No source consulted reconciles the two. The site covers 155 feddans on the east bank of the Suez Canal.51
What worked
The delivery. Construction ran from September 2019 to May 2021, under two years and through the pandemic.1 ENR named it Global Project of the Year for 2021, and MEED lists it among past winners of its regional Project of the Year award.112 Orascom reports more than 22 million hours worked without a lost-time injury, which is the contractor’s own figure.5
Two design decisions deserve credit. The team moved the plant from the west bank to the east because the western site could have been farmed, and paid for 6,500 piles to stabilise the sandy soil there.1 And 16,000 square metres of solar sludge drying, the first in Egypt, dry the cake by a further half using sunlight rather than fuel.1
It also built a capability. The same two contractors, joined by Hassan Allam and Metito, went on to build the larger New Delta plant at Dabaa.13 Egypt can now deliver water infrastructure at this scale largely with Egyptian contractors.
What did not, or is unresolved
The salt. A 2026 study in Scientific Reports, written by Benha University with the Nile Research Institute and the Drainage Research Institute of Egypt’s National Water Research Centre, identifies the feeder supplying the plant as a compliance hot-spot. Baseline salinity there runs about 2,200 ppm against a regulatory reuse limit of 2,000.7 The authors are blunt about the arithmetic. Restoring compliance by dilution would need a 15.8 per cent increase in Eastern Delta freshwater, which is unattainable under a fixed Nile allocation. Even relaxing the standard to 2,500 ppm does not fix it.7 Their conclusion is that no realistic adjustment to mixing ratios or standards can restore compliance, and that pretreatment is required regardless of freshwater availability.7
The plant as built removes no salt. Its published process stages address turbidity, organics and pathogens, and none is designed to remove dissolved salts.32 A plant sized for the wrong constraint is still a large and competent plant, but it is not a solution to the constraint that governs reuse.
Nor is it treating most of the problem. Lake Manzala still takes over 95 per cent of its inflow, about 7,500 million cubic metres a year, from six mostly untreated drains, Bahr El-Baqar among them.14 A peer-reviewed assessment of the lake in 2026 credits the plant and the dredging with improved circulation, and still finds Manzala hypereutrophic with a heavy metal pollution index above 180.14
The water also has to arrive. The plant was finished in May 2021.1 The two conveyance routes taking its output into the Sinai reclamation areas were about 89 per cent complete in August 2026, five years after the ribbon was cut.15 Two of its three Guinness records, for the largest water treatment plant and the largest sludge treatment plant, passed to the New Delta plant at Dabaa in 2023.51316
What is missing from the record matters as much. No published measurement of the plant’s actual effluent was found. Egyptian standards prohibit treated wastewater on raw vegetable crops, and nothing establishes what is grown with this water or on how many feddans.17 Orascom reports an operation and maintenance contract running from December 2021, but its terms, operating costs and energy use are not public.18 An evaluation in Frontiers in Water put the surrounding problem plainly: public critical assessments of Egypt’s water megaprojects were not detectable.19
What it means for the next one
Design for the constraint that governs reuse, not the one that is easiest to engineer. A physico-chemical train sized for turbidity and pathogens is the right answer to a different question. Where the limiting factor is salinity, the treatment choice is settled before the tender, and the Egyptian institutes say so in terms: pretreatment is required regardless.7
Treat salinity at the sub-basin rather than the outfall. The same paper points to upstream source control, citing work in which treatment at sub-basin outlets combined with lined channels achieved a 75.67 per cent reduction in dissolved solids.7 A network of smaller interceptors also avoids concentrating a whole basin’s salt load at one point.
Specify the target as a share of basin load, not as plant size. A plant on one drain, while the lake still takes most of its inflow untreated, helps explain why a record capacity did not produce a restored water body.14 Build the conveyance before the opening, and publish the effluent data. Without it, a plant of this scale is judged on a certificate rather than on what comes out of the pipe.
Sources
19 references
Contractor and state capacity, safety and award figures are treated as claims. A widely cited May 2025 Mada Masr figure for total drain flow into Lake Manzala could not be retrieved and is not used. The Arab Fund loan record was read from an archived copy.
- McFarland, P. (2021), “2021 Global Project of the Year and Best Water-Wastewater: Bahr Al Baqar Water Reclamation Plant”, Engineering News-Record, 8 December 2021.
- Egyptian State Information Service, “Guinness Record: Bahr Al Baqr project certified as biggest wastewater plant worldwide”, 28 September 2021.
- ACCIONA, “Bahr Al-Baqar WWTP”, project page.
- Daily News Egypt, “Arab Contractors, Orascom Construction, Engineering Authority ink contract for water treatment of Bahr Albaqar drain project”, 1 May 2019.
- Orascom Construction, “Orascom Construction-Arab Contractors JV inaugurates the world’s largest water treatment plant”, 29 September 2021.
- Soliman, R.M., Othman, B.A., Shoman, S.A., Gado, M.M. and Azzam, M.I. (2022), “Assessment of Bahr El-Baqar drain and its environmental impact on Manzala Lake in Egypt”, Journal of Ecology and Natural Resources 6(3): 000291, full text (PDF), 21 July 2022.
- Abdul-Muttalib, A., El-Saadi, A., El-Gazzar, H. and Refaey, M. (2026), “Projecting water availability and quality for reuse in the Bahr El-Baqar catchment”, Scientific Reports, full text via PubMed Central, 4 May 2026.
- Ministry of Water Resources and Irrigation (Egypt), Bahr El-Baqar treatment plant project.
- The Arab Contractors, “Bahr El Baqar Water Treatment Plant”, project page.
- Arab Fund for Economic and Social Development, “Construction of Bahr El-baqar Drain System”, loan no. 657, board approval 5 May 2018 (Internet Archive copy of 20 March 2025; the live page blocks automated access).
- PROCESS Worldwide, “Insight into the world’s largest water treatment plant”, 9 May 2023, citing the Egyptian Presidency.
- MEED, “MEED announces Mena’s best projects”, 21 September 2022.
- Guinness World Records, “Largest water treatment plant”, New Delta Irrigation Water Treatment Plant, Dabaa, achieved 26 July 2023.
- Eissa, M.A., El Sayed, S.M., ElSayed, F.A., Askalany, A. et al. (2026), “Evaluating the restoration of Egypt’s Mediterranean Manzala Lagoon: a multi-index assessment of water quality and heavy metals”, Scientific Reports, full text via PubMed Central, doi:10.1038/s41598-026-45115-x.
- Daily News Egypt, “Egypt launches new water year with expanded reuse, digital transformation and climate resilience projects”, 1 August 2026.
- Guinness World Records, “Largest sludge treatment plant”, New Delta Irrigation Water Treatment Plant, Dabaa, achieved 4 August 2023.
- Abdella Ahmed, A., Shalaby, M., Negim, O. and Abdel-Wahed, T. (2022), “Egyptian reuse standards of treated wastewater for irrigation: a comparative study of physico-chemical and agronomic controls”, Mansoura Engineering Journal 47(2), abstract, on Egyptian code ECP 501/2015.
- Orascom Construction, “Bahr El Baqr Wastewater Treatment Plant”, operation and maintenance project page.
- Ellermann, A.-K., Hamhaber, J. and Al-Saidi, M. (2026), “National development in post-revolutionary Egypt: sustainability through water megaprojects?”, Frontiers in Water, full text, 16 April 2026.
Numbered references are linked from the superscript markers in the text. Figures without a marker come from the sources above as compiled in the site methodology.